Municipality's Response to the Moerdijk High-Voltage Substation Plan 

TenneT and Enexis want to build a high-voltage substation between Zevenbergen and the village of Moerdijk. The municipality of Moerdijk has carefully reviewed the plans and has concerns.

View of a high-voltage substation

To illustrate, here is a photo of the current 380-150 kV high-voltage substation in Diemen. This high-voltage substation has less capacity and also lacks a 20 kV medium-voltage substation. As a result, this substation covers a smaller area of approximately 16 ha.

TenneT and Enexis, the operators of the national and regional power grids, want to build a large combined high-voltage substation in Moerdijk. To that end, they are choosing between two locations adjacent to the port and industrial area on the side of the village of Moerdijk: on Krukweg or on Gorsdijk. The municipality of Moerdijk has reviewed the plans and has concerns.

Illogical and unsubstantiated

There is no doubt that the power grid needs to be expanded. However, the choices outlined in the plan are illogical and poorly substantiated in a number of respects. The municipality has outlined these points in a so-called “statement of views”: an official response to TenneT. The summary below outlines the key points from the statement of views.

Want to leave a comment yourself?

Would you like to comment on the plan yourself? You, too, can submit a statement of opinion. The deadline is Thursday, June 18, 2026. A statement of opinion is not an official objection. It is a comment that TenneT will take into account when making a final decision. You can file an official appeal against the final decision, but only if you have first submitted a statement of opinion.
You can also find instructions on how to submit a statement of opinion in the summary.