Work Begins on New Rilland–Tilburg High-Voltage Transmission Line

On November 4, preparatory work will begin, commissioned by TenneT, for a new overhead high-voltage transmission line between Rilland in Zeeland and Tilburg in Brabant. In the coming months, contractors will begin work on the temporary connections in Standdaarbuiten and other locations.

The schedule below outlines what the Sluissedijk neighborhood can expect in the coming period.

  • November 2024: Traffic measures and construction of access roads and work sites.
  • January 2025: Installation of temporary takeoff points.
  • April–May 2025: Installation of temporary cables between the takeoff points and installation of safety fences.
  • May–July 2025: Removal of conductors from the poles and reconnection of conductors to the temporary feed-in points. Commissioning of the feed-in points.
  • August 2025: Completion, including cleanup of access roads and work sites.

Please note: This is an abridged version of a press release from TenneT. The full press release is available on the project website: Work Begins on New Rilland–Tilburg High-Voltage Transmission Line