October 3: Information Session (Afternoon/Evening) and Public Comment Period for New TenneT Project in Moerdijk

The electricity we use is increasingly being generated sustainably by wind turbines in the North Sea. To connect a new offshore wind farm to the onshore power grid, grid operator TenneT plans to begin laying an underground power cable and constructing a so-called converter station around 2027. Four possible routes for this connection have been studied, along with eleven potential locations for a new converter station. Our municipality is located within the project area for the cable and the converter station.

Comparative study completed 

Over the past few months, studies have been conducted to ensure that all routes and locations can be properly compared . The most significant impacts of the project on the environment, the surrounding area, the required technology, costs, and relationships with other planned projects are outlined in the reports “Comprehensive Impact Analysis” and “Environmental Impact Report, Phase 1.”  

You can now respond 

Through October 31, 2024, you may submit feedback on this report to the Ministry of Climate and Green Growth. You can do so by filling out the online feedback form on the RVO website, by calling, by sending a letter to the Energy Projects Office, or during office hours at City Hall or at one of the drop-in evenings in other municipalities. Contact information is available on the website mentioned above.  

Office Hours 

On Thursday, October 3, there will be a public consultation session at the town hall in Zevenbergen. You are welcome to stop by between 2:00 p.m. and 5:00 p.m. and between 6:00 p.m. and 8:00 p.m. to get more information, ask questions, or submit feedback. In addition to “Net op zee Nederwiek 3,” the following projects will also be represented: 

If October 3 doesn't work for you, you're also welcome to join us between 7:00 p.m. and 9:00 p.m. at: 

  • De Witte Leeuw in Raamsdonksveer on Wednesday, October 2 
  • Streona Village Hall in Strijen on Monday, October 7 
  • Ons Dorpshuys in Drimmelen on Thursday, October 10 
  • Jan Blanken Dry Dock in Hellevoetsluis on Tuesday, October 15 
  • Rijkswaterstaat’s Offshore Expertise Center in Stellendam on Wednesday, October 16  

This fall, the Minister for Climate and Green Growth will select a cable route and a location for the converter station 

By the end of 2024, the Minister of Climate and Green Growth will select one preferred route and one preferred location for the project. This preferred route may be a combination of sections from the routes currently under consideration. According to the schedule, construction will then begin around 2027, and the project could become operational in 2031. The cable will be laid using open-cut trenching or drilling. In terms of appearance, the converter station will be similar to a distribution center covering approximately 5.5 hectares.   

More information 

Watch the explanatory video about this project and view the interactive map on the TenneT website.

Curious about other energy projects in your area? Check out the digital project map at www.bureau-energieprojecten.nl and search for your address. Or go directly to the project pages for other projects: 