Status Update on the Moerdijk Waterfront Project

Following the relocation of the truck parking lot, the second phase of the Waterfront project in Moerdijk is also nearly complete. This phase consisted of work on the dike and is likely to be fully completed this year. The third phase—the port redevelopment—will begin next year. Last week, Rijkswaterstaat issued the permit required to renovate the port.

Start of the bidding process

With the permit now in hand, the Municipality of Moerdijk can begin drafting the documents for the European tender for the port development. The tender process can then be launched before the end of the year. This means that by the first quarter of 2025, it will be known which contractor will be selected. At that time, it will also become clear how much the port development will cost and whether the funds made available by the city council in 2022 are still sufficient to carry out the work.

Delay

In 2023, the project was delayed by one year due to uncertainty surrounding nitrogen regulations. As a result, the planned implementation of the port redevelopment was pushed back from 2024 to 2025. If all goes according to plan, the harbor will be renovated by the end of 2026. After that, the fourth and final phase can begin: residential construction on the west side of the harbor (2027–2028).

A Look Back at the Second Phase

Work on the dike project is nearly complete. The wheelchair-accessible ramp and the walking path along the top of the dike have been completed. After the construction industry’s summer break, the contractor will put the finishing touches on the project. The additional dike stairs are expected to be installed next month due to a delay in the delivery of the necessary building materials.