Groot onderhoud Zeestraat, Willem-Alexanderlaan en Doctor Ariënslaan in Zevenbergen

What's coming up?
We are conducting major maintenance on Willem-Alexanderlaan, Doctor Ariënslaan, and Zeestraat.
We will be:
- reduce the speed to 30 km per hour;
- replace the sewer;
- repaving the street;
- lay new sidewalk pavers;
- and make the area greener.
What is the latest update?
Before we begin, Brabant Water will first replace the water mains. You will receive a letter from Brabant Water regarding this. This work began on Monday, October 19, and will take approximately 40 weeks.
Removing Trees
As part of the work on the cables and pipes and the subsequent landscaping, we will need to cut down a large number of trees. We understand that trees are important to the green character of your street. However, this is necessary for several reasons:
- Space for the new layout. Not all trees can remain in their current locations.
- Future-proof green spaces. We want to give the trees enough space to grow healthily and safely.
- There are cables and pipes underground. The tree roots could get in the way during the work.
- Damage caused by tree roots. In several places, the roots are pushing up the pavement. This creates uneven sidewalks and can lead to dangerous situations.
The trees will be removed in several phases. We will coordinate this with the schedule for work on the cables and pipes. This will ensure that trees are not removed any sooner than necessary.
Information Evening
On Tuesday, September 22, the second informational meeting took place at City Hall. During the event, the civil engineering design was presented, and attendees had the opportunity to ask questions.
Were you unable to attend? The design is available for viewing as a PDF at the bottom of this page.
- A roadway with bike lanes on both sides.
- Parking spaces along various sections of the street.
- Sidewalks along the houses.
- Green belts with trees along the street. The landscaping plan will follow later
- Redesign of various intersections and connections to side streets.
- Intersections present a visual barrier
Drawing 2: Zeestraat–Willem Alexanderlaan, Part 1
- Redesign of Zeestraat and Willem-Alexanderlaan. Both will have a speed limit of 30 kilometers per hour.
- Roadways with sidewalks and parking spaces with an open-surface pavement.
- Green belts with trees along various sections of the roads. The landscaping plan will follow later.
- Redesign of intersections and crosswalks on Willem-Alexanderlaan.
- Bike lanes marked in red on Willem-Alexanderlaan.
- The Zeestraat roadway will be paved with cobblestones
Drawing 3: Zeestraat–Willem Alexanderlaan, Part 2
- Redesign of Zeestraat and Willem-Alexanderlaan. Both will have a speed limit of 30 kilometers per hour.
- Roadways with sidewalks and parking spaces with an open-surface pavement.
- Green belts with trees along various sections of the roads. The landscaping plan will follow later.
- Redesign of intersections and crosswalks on Willem-Alexanderlaan.
- Bike lanes marked in red on Willem-Alexanderlaan.
- The Zeestraat roadway will be paved with cobblestones
Where is this location?
Planning
-
Information Fair
After the summer of 2025
-
Start of Work
Q3 2027
You will receive the letter from Brabant Water prior to the start of the work.
Contact
Do you have any questions? Please contact us atomgevingsmanagement@moerdijk.nlor085 – 822 04 19.