Projects in Zevenbergen

On this page, you'll find a list of all construction projects and scheduled maintenance in Zevenbergen.

We’re getting to work at the Watermolen. We’ll be performing maintenance on the pavement and the green spaces. This means we’ll be repaving the area and, if necessary, doing minor landscaping work. We’ll be using new materials for this. The work will take place on the roadway, the sidewalk, and near the parking spaces. The image below shows where we’ll be working.

Planning

Work on the Watermill began on April 27, 2026, and, if everything goes according to plan, is expected to last until mid-September 2026.

How does this make you feel?

Work will begin in the first quarter of 2026 and will be carried out in phases. The street will be closed to traffic during the work.
Your home will remain accessible: on foot or by bicycle (pushed by hand) via temporary walkways.
Residents living nearby will be notified in advance by mail. The contractor will inform the neighborhood of the exact start date in a timely manner.

Contact

Do you have any questions or comments regarding this letter? Please feel free to contact our Community Relations Manager, Aida Humic-Omicevic. She will be happy to assist you.

You can reach her at:
Email:omgevingsmanagement@moerdijk.nl
Phone: 14 0168

What are we going to do?

On behalf of the municipality of Moerdijk, contractor Elshout en de Bont is repaving Fabrieksstraat. The project includes the roadway, sidewalks, parking spaces, and the parking lot at the fire station. Preparations have already begun. Below is a view of the work area where we will be working.

Planning

Work on Fabrieksstraat began in late April 2026 and, if everything goes as planned, will continue through late July 2026.

How does this affect you?

Work will begin inthe second quarter of 2026and will be carried out in phases. The street will be closed to traffic during the work.

Your home will remain accessible: on foot or by bike (pushing it along) via walkways.

Neighbors will be notified in advance by mail. The contractor will inform the local community of the exact start date well in advance.

Contact

Do you have any questions or comments regarding this letter? Please feel free to contact our Community Relations Manager, Aida Humic-Omicevic. She will be happy to assist you.

You can reach her at:
Email:omgevingsmanagement@moerdijk.nl
Phone: 14 0168

What are we going to do?

On behalf of the municipality of Moerdijk, contractor Elshout en de Bont is carrying out maintenance work in the Wede and Repel in Zevenbergen. The work involves repairs to the sewer system and street paving.

Planning

Work on the Wede and Repel rivers will begin in early May 2026 and, if everything goes according to plan, is expected to last until early November 2026.

How does this affect you?

Work will begin inthe second quarter of 2026and will be carried out in phases. The street will be closed to traffic during the work.
Your home will remain accessible: on foot or by bicycle (pushed by hand) via temporary walkways.
Residents living nearby will be notified in advance by mail. The contractor will notify the neighborhood of the exact start date in a timely manner.

Contact

Do you have any questions or comments regarding this letter? Please feel free to contact our Community Relations Manager, Aida Humic-Omicevic. She will be happy to assist you.

You can reach her at:
Email:omgevingsmanagement@moerdijk.nl
Phone: 14 0168

On Achterdijk, there is a problem with traffic driving too fast. In response to requests from the local community, Achterdijk is therefore being redesigned. This design was developed in collaboration with residents, who were given the opportunity to choose the type of speed-reduction measures and their locations. A study is also being conducted on adjusting the village boundary.

What's coming up?

Various speed-reduction measures will be implemented on Achterdijk. Residents have opted for road narrowings, as well as optical speed bumps, red bike lanes, and at-grade intersections.

In addition to the desire to reduce the speed limit on the Achterdijk, there was also a request to adjust the town limits. This proposal is now being submitted to the council. If it is approved, the adjustment of the town limits can also be included in the project.

What is the latest update?

The engineering firm reviewed the residents' preliminary design for safety and accessibility. A final design was then developed based on this. Curious?

View the Achterdijk – Blokweg – Nieuwe Weg

  • Red-colored bike lanes will be added on both sides of the roadway;
  • There will be road narrowings near house numbers 15, 81, 91, and 97;
  • Speed bumps will be installed near house numbers 49, 51, and 89;
  • The intersections with Nieuwe Weg and Molenweg will be made equivalent. These intersections are designed as simulated plateaus and will be painted red.
  • The road markings are being repainted;
  • The sign marking the boundary of the Achterdijk will be located near Achterdijk 41a.

View the Achterdijk – Nieuwe Weg – Gelderseweg

  • Red-colored bike lanes will be added on both sides of the roadway;
  • There will be road narrowings near house numbers 105, 107, 109, 119, 125, and 171;
  • Speed bumps will be installed near house numbers 107, 107b, 24a, 123, 127, 143, and 179;
  • The intersections with Schenkeldijk and Drielseweg will be made equivalent. These intersections are designed as pseudo-plates and will be colored red;
  • The road markings are being repainted;
  • The asphalt between Drielseweg and Gelderseweg is being repaved;

The sign marking the municipal boundary for Kalishoek will be placed near Achterdijk 127 and will extend to the intersection with Gelderseweg.

Planning

Now that the design drawings are complete, the bidding process can begin. We expect to know who will be carrying out the work by August 2026. After that, a schedule will be drawn up with the contractor. More information about the schedule during construction will follow.

Contact

If you have any questions for the municipality, please contact our environmental manager. You can easily do so by emailing omgevingsmanagement@moerdijk.nl or calling 085 – 822 04 19.

On Monday, August 31, 2026, the Municipality of Moerdijk and BAM Infra will begin work on Afgebrande Hoef in Zevenbergen. From August 31 through December 31, 2026, Afgebrande Hoef will be closed to all traffic. The current road will be removed. Afterward, the new construction road, Verlengde Zuidrand, will be built here. Traffic heading toward Markdijk will be rerouted via Prins Hendrikstraat, Kristallaan, and Generaal Allenweg.

The work is necessary for the development of the Zevenbergen-Oost area. In addition, work is underway on the new construction road, Verlengde Zuidrand. At the same time, cables and pipes are being upgraded. By carrying out this work simultaneously, the project will be completed more quickly.

On Monday, August 31, 2026, the Municipality of Moerdijk and BAM Infra will begin work on Hazeldonkse Zandweg in Zevenbergen. From August 31 through November 13, a section of Hazeldonkse Zandweg will be closed to motorized traffic. This section runs from the bridge over the Zwanengat to the roundabout at Hazeldonkse Zandweg 34, a distance of approximately 300 meters.

Detours

  • Traffic heading toward downtown Zevenbergen should take the Oostrand (N389) and Prins Hendrikstraat.
  • Traffic heading toward Etten-Leur should take Prins Hendrikstraat and Oostrand (N389).

Cyclists and pedestrians can continue to use Hazeldonkse Zandweg.

On behalf of the municipality of Moerdijk, contractor Lindeloof B.V. is performing maintenance on the existing path.

What are we going to do?

The separate path along Perzikkruid is in need of maintenance. During the project, we will carry out repair and maintenance work on the existing path where necessary.

Work will begin on September 28, 2026, and is expected to last until mid-November 2026.

How does this affect you?

The pedestrian and bike path is separate from the homes. Therefore, we expect minimal disruption for nearby residents. During construction, part of the path may be temporarily closed. Pedestrians and cyclists will then follow a detour. We will try to minimize any inconvenience as much as possible.

Contact

Do you have any questions about the construction work? If so, please contact the municipality’s civil engineering project manager: Dennis van de Luijtgaarden.

He can be reached at the following email address: dennis.van.de.luijtgaarden@moerdijk.nl or by phone at 14 0168.

On behalf of Brabant Water and Enexis, BAAS Verkley is carrying out work on cables and pipes on Zeestraat in Zevenbergen. They would like to inform you about this work.

Please note! These construction activities are not being carried out by the municipality of Moerdijk.

Below is a summary of the most important information for you:

  • Work will begin on Monday, October 19, 2026. It will take approximately 40 weeks.
  • During the work, you may experience brief interruptions in your water or gas service at times. Brabant Water or Enexis will notify you of this at least 48 hours in advance via a notice or letter. Keep a close eye on your mailbox!
  • The old pipes are made of asbestos cement. For safety reasons, we therefore store these items in sealed containers. Please keep them closed.
  • After the pipes have been installed and removed, contractor Baas B.V. will restore the pavement.
  • To ensure the work can be carried out properly, a storage facility is being set up on Galgenweg.

Expected Disruption

The street has been dug up during the construction work. You may also experience some noise, dust, and loose sand. Finally, some parking spaces will be temporarily closed. Want to know more? Then watch this video.

Questions or Complaints

For the latest information on service disruptions, please visit:

Do you have any questions about the construction work, the gas line, or the water line? Below are the contact details for each party: